2. Zone 4

Step #01 Assembling the Pipe 1/2

List of Components

ItemSpecQty
 Pipe section Ø50 - 680mm1
 Pipe sectionØ50 - 220mm1
 Pipe sectionØ50 - 90mm2
 Pipe 90° connectorØ50 mm2
 Pipe T connectorØ50 mm1

Tools needed

Measuring Tape

Instructions

  1. Slide the 90° connector in the 680mm tube section.
    1. Slide the T-connector on the other end.
      1. Slide the 220mm pipe section in the T-connector.
        1. Slide the two 90mm pipe section in both connectors.
          1. Slide the 90° connector in the 220mm pipe section.
            Use liquid soap to ease the pipe assembly.

            Animation